Corydon- New Middletown Roadway Design Phase I

This project consisted of final design for approximately 4,940 feet of roadway along Corydon-New Middletown Road beginning at the existing bridge over Little Indian Creek.  Work consisted of producing final construction plans, right-of-way plans, utility relocation plans, right-of-way acquisition, surveying and geotechnical work.

The geotechnical work associated with this project consisted of 10 soil borings along the centerline of the roadway alignment (locations were determined by the design engineer) and also included an analysis of soil stability issues along the west side of the roadway near the bridge.

 

  Project Features

Final Roadway Design

Right-of-Way Acquisition

Utility Relocation Coordination

Geotechnical Analysis

Construction Administration